Platteville Fire Facility Construction Update


Retired Fire Fighter and Optimist Member Paul Budden donned his fire helmet to update us on the construction progress at the new Platteville Fire Facility. A feasibility study for the project was begun in 2022, and in 2023 the Fire Facility Capital Campaign Fundraising Committee was tasked with raising an additional $1.5 million for costs not covered by the federal appropriation grant, the city or the townships.  To date, they are just over $300,000 over their $1.5 million goal, and that has allowed the department to acquire items they had to delete to get under budget.  One item Paul mentioned was a forced entry door that can be used for training purposes.  Construction is currently moving along, with an August 2026 completion date and full occupancy date of October 2026. Click the link below to see a slideshow of the construction progress: https://youtu.be/GjeKGm8QWUo